Virginia class still 'disciplined program'

From The Naval Submarine League

http://www.navalsubleague.com/ 

  By Robert A. Hamilton - New London Day

  Although the Navy has allocated $9.5 billion for building the first four submarines of the Virginia class, the bill is now expected to reach about $10.7 billion.

 Yet there has been no congressional outcry.

  Pentagon reports still laud the program - it was the only Navy program singled out in a Department of Defense report on transforming the military as examples of weapons systems designed for the 21st century - and senior

 Navy officers continue to support the Virginia program as a model for procurement.

  "This program has been described as the most disciplined in the Pentagon, and we aim to keep it that way," said Adm. Frank L. "Skip" Bowman, head of the Naval Reactors program.

  Bowman noted that the tentative schedule for filling the reactor plant with water was December 2000; over more than five years, there was less than two  months delay from that original plan, he said. "It is happening, and it is  on schedule."

  Rear Adm. John P. "Phil" Davis, who just finished a tour as program executive officer for submarines at the Naval Sea Systems Command (NOTE: This is erroneous. RADM Davis remains the PEO), said about 50 percent of the  drawings of the Virginia class were done by the time construction started, compared with 1.6 percent of drawings for the Ohio and 5.6 percent for Seawolf. That means there are fewer expensive change orders required once construction begins.

  In addition, Electric Boat in Groton, which designed the submarine, has come up with a number of innovations that will make the process more efficient.

  For instance, the combat control suite has been designed as a module that can be tested electronically, then installed as a single piece. In previous classes, the combat system was assembled in a room, tested, then dismantled and reassembled in a submarine, where it had to be re-tested to make sure there were no problems.

 "This combat system module is working now, three years before delivery," Davis said. "We're ready to go to two or three (Virginia-class submarines) a year,or whatever the nation wants us to do."

 Rear Adm.-select Paul Sullivan, who succeeded Davis as program executive officer for submarines,  (NOTE: This is erroneous. RDML(Sel) Sullivan remains the Virginia Class Program Manager) said Virginia will also be the easiest submarine to build, operate and eventually to decommission, because for the first time engineers sat down with the shipyard workers and sailors to discuss the design before it was committed to the computerized drafting program.

 Previously engineers came up with a design and gave it to the builders, and the operators had to live with the results.

 "We learned in the past how inefficient that process was," Sullivan said.

 "We said, 'Everyone is going to be at the same table the same day on theVirginia,'... and the process really works."

 Why such praise for a program that, on paper at least, is 12 percent over  budget? Backers of the Virginia class say the difference in what the program has, and what it needs, is due in large part to factors that were beyond the control of the submarine program office.

  Inflation

 The largest piece driving the budget shortfall, about $600 million, was due to inflation. The Navy was only allowed to use a 2-percent inflation estimate for the project, which it knew from the start was going to be low, according to Bowman.

 In fact, inflation has been higher even than what the Navy estimated. Due to a good economy,shipyard payrolls have had to increase to match wages in  other sectors.

 Material and equipment costs have also gone up much more rapidly than  expected because of the inefficiencies of low-rate production - if you're only buying four reactors over five years, for instance, the cost is considerably higher than buying two a year.

 Sullivan said another problem is that many Seawolf suppliers quoted prices  for quieted, shock-hardened components that were based on the expectation that 29 ships would be built.

 Instead, the Navy cancelled the program after three.

 "We're not going to get a price break on Virginia until we start building  more than one a year," Sullivan said. "The inflation rate in this industry is killing us."

 He estimated that in some areas inflation is running 7 percent a year. And  because it will be 12 years from the time the Navy orders the first Virginia until it takes delivery of the fourth ship, that gives a long time for those  inflationary pressures to increase.

  Other shortfalls

  Another big piece of the deficit is money that was taken "off the top" of the Virginia program to cover shortfalls in other Department of Defense programs, which amounted to about $339 million, Bowman said.

 Because the last dollar for the Virginia program won't have to be put up  until 2008, he noted, there has been no hurry to put it back, but he said he is confident that it will be restored.

 Sullivan also said that some of the increases need to be put into historic  context. The cost of the design contract, for instance, made up $1.45 billion of the original $9.5 billion estimate. That will be over budget by about $188 million.

 "That's the best we've ever done; Seawolf went over by 100 percent, for  various reasons," Sullivan said. "But it's a small percentage of a big number, so it's still a big number."

 Another change came in the way the Navy procurement system works.   Previously, many of the engineering services provided by the Naval Sea  Systems Command did not come out of the submarine budget.

 Because of an accounting change, those services are now billed to the  submarine program. There has been no change in the price to taxpayers,  Sullivan said, just in the way the cost is allotted. But the result is, the  Virginia tab took a $155 million jump.

 There have been several smaller increases as well.

 The Navy learned from the Seawolf program that applying a new, quieter hull coating is more difficult than expected. That raised the price by about$65 million.

 Changes in the ship design and in crew berthing requirements raised the  price another $26 million, or about one-third of 1 percent.

  "I think that number shows that when it came to new requirements, we didn't go adding a lot," Sullivan said.

 Sullivan also noted that there has been a lot of attention paid to overruns in the combat system on the Virginia.

 The original contract called for the development to cost about $156 million, and it went about $80 million over that, but it will be spread over an  estimated 30 ships.

 

 The Navy spent almost $1.5 billion developing the combat control system on the Seawolf, and those costs will be amortized over three ships.

 "Even with the overrun, it's a tremendous increase in capability at a fraction of the cost," Sullivan said. "Nobody is happy about a shortfall of funds when you have to dig deep into your pockets to cover it. But everyone seems to understand."

  The best in design

 Sullivan said based on some rough numbers that came out of his office, if  the Navy were to restart production of the Los Angeles class - the last one was completed in 1996 at a cost of more than $1.2 billion - it might save 5 to 10 percent over the cost of building the Virginia class.

 "You'd get a ship that doesn't even come close to how quiet the Virginia is, that can't match it for speed or capability," Sullivan said. And, he said, there would be a very large one-time cost to redesign the Los Angeles for modern technology.

 Sullivan noted that he has been involved in the development of the Los  Angeles, Ohio, and Seawolf classes, before his experience with Virginia.

 "I'd have to say this is by far the best in design and construction," Sullivan said. "And the best way I know to solve these problems is to put more ships in the budget. If we could get out of low-rate production, a lot of these issues would work themselves out."